Harbury Cutting, Leamington Spa

Harbury Cutting, Leamington Spa

J Murphy use Central Alliance as strategic pre-construction partner at Harbury Cutting, Leamington Spa

Technology unlocks ground movement and geospatial information

 

Project Background

 

Harbury cutting was excavated in 1847 by Brunel as part of the construction of the main Oxford to Birmingham line and at the time, was considered to be a significant engineering feat.  At over 34 metres deep, the cutting was the largest man-made cutting in the world that was dug entirely by hand!

 

There is a history of geotechnical failures associated with the cutting, in fact it has suffered from persistent stability issues for the last 20-30 years and landslips have been a regular occurrence.  J Murphy were working on a scheme designed to resolve these stability issues.

 

Whilst working on the project, tension cracks started opening up in the slope above the cutting in late 2014 and investigations of the incident showed that there was a previously unrecorded vertical fault at the back of the cutting that had not shown on up on geological maps or in previous investigations.  During construction in late January 2015 a large landslide occurred that resulted in the movement of 350,000t of material. J Murphy had already moved 30,000t from the failed slope.

 

 

Project Scope

Central Alliance were brought in to accelerate the progress of the slope stability project.  Initially, the remit was to help speed up ground investigation works and also to install ground movement and ground water monitoring instruments.  After the large landslide, the project scope widened and accurate geo-referenced survey data was required.

 

 

Deliverables

 

  1. Initial GI work (rotary drilling) for J Murphy was carried out prior to the landslide to establish further information on the ground conditions of the cutting.
  2. Further GI works were commissioned following the landslide in order to gain a better understanding of the geology and to facilitate the construction of a 3D geological model of the site to aid design.
  3. Following rapid response on the day of the large failure Central Alliance were then commissioned to carry out a UAV aerial topographical survey and also used HD aerial video photography in order to establish the scale of the landslide that would enable remediation works to be planned efficiently. This was all undertaken in the days immediately following the failure.
  4. In addition, we installed de-watering wells and a full dewatering system in order to ensure ground water levels were reduced to try and minimise the risk of further instability during construction.  Inclinometers were also installed and daily monitoring of ground movement and ground water levels was carried out and reported on.
  5. Our senior team were also part of the Harbury emergency working party, contributing and consulting from a GI and geology perspective.
  6. We introduced our satellite monitoring solution to establish land movements over time on various areas of the Harbury site.  Regular long term monitoring would help to establish how the land has responded to the remediation works.

 

 

Benefits

 

  • Major works completed within specific time frame to a high standard
  • Pre-construction services including GI, surveying, instrumentation and monitoring are managed through one organisation, minimising risk, and improving communication and overall operations.
  • Central Alliance’s expertise and experience delivered high quality pre-construction services on such a high profile project and provided J Murphy with peace of mind and confidence throughout.
  • New and innovative technology used to give comprehensive site data and improve knowledge so that the best recommendations/solutions could be put in place.